Queensland Court Deadlines Before Christmas 2026 for Creditors Chasing a Debt
Summary
How the court holiday, the registry's open days and the judges' sittings bear on a Queensland business chasing a debt through a statutory demand or a default judgment before Christmas and why a subcontractor's payment claim and a supplier's retention of title terms keep a timetable of their own.
Key Takeaways
- Supreme, District and Magistrates Court registries close for court holidays from Friday 25 December 2026 to Friday 1 January 2027; Thursday 24 December is the last ordinary filing day and Monday 4 January 2027 the first day open.
- When this guide was written, the Supreme Court's calendar showed no applications judge from Monday 21 December 2026 to Friday 1 January 2027, which made Friday 18 December the last ordinary day for a contested application there.
- The 21 days on a statutory demand served on Thursday 3 December end on Thursday 24 December; they are calendar days and keep running through the closure.
- A claim served by hand on Monday 16 November leaves eight registry days before the closure to request default judgment; on a claim served after Wednesday 25 November the request waits until 2027.
- A subcontractor's construction payment claim and a supplier's retention of title terms run to clocks of their own that the court holiday does not set.

- 1.Which calendars set the December deadlines?
- 2.Which dates matter, working back from Thursday 24 December?
- 3.How do the 21 days on a statutory demand run over Christmas?
- 4.When can a creditor request default judgment before the closure?
- 5.Why do subcontractors and suppliers on retention of title terms run to a different timetable?
- 6.Matching the document to the debtor
- 7.Frequently Asked Questions
A Queensland creditor that wants judgment entered before Christmas or the 21 days on a statutory demand over by then, is working to Thursday 24 December 2026, the last ordinary registry day before the court holiday. On service by hand, a demand's 21 days end by 24 December only if it is served by Thursday 3 December and default judgment can be requested before the closure only on a claim served by Wednesday 25 November. Astris Law in Brisbane counts back from 24 December through the court holiday, the registry's open days and the judges' sittings, then looks at subcontractors and suppliers on retention of title terms.
Which calendars set the December deadlines?
Supreme Court Practice Direction 2 of 2026 designates each day from Friday 25 December 2026 to Friday 1 January 2027 as a court holiday for r 976 of the Uniform Civil Procedure Rules 1999 (Qld) (UCPR) and the District Court (Practice Direction 2 of 2026) and the Magistrates Courts (Practice Direction 1 of 2026) designate the same days. Four are public holidays (25, 26 and 28 December and 1 January); 29 to 31 December are court holidays only.
Rule 976 requires a registry to be open on each day other than a Saturday, a Sunday or a court holiday, so Thursday 24 December is the last ordinary filing day and Monday 4 January 2027 the first day open again. The Supreme Court's civil applications availability calendar showed, when this guide was written, no applications judge from Monday 21 December to Friday 1 January, which made Friday 18 December the last ordinary day for a contested application there. The District and Magistrates Courts set their own December lists, which creditors there should check.
Which dates matter, working back from Thursday 24 December?
The dates assume service by hand and exclude the day of service.
| Date | What it is |
|---|---|
| Mon 16 Nov 2026 | The 28 days on a claim served on this day end on Mon 14 Dec. |
| Wed 25 Nov 2026 | Last day to serve a claim for its 28 days to end on Wed 23 Dec, leaving Thu 24 Dec as the one registry day to request default judgment before the closure. On a claim served Thu 26 Nov the 28 days end on Thu 24 Dec and the request waits for 4 Jan. |
| Fri 27 Nov to Sun 29 Nov 2026 | The 28 days on a claim served in this window run to Mon 4 Jan 2027. On a claim served later the request for default judgment also waits until 2027. |
| Thu 3 Dec 2026 | Last day to serve a statutory demand for the 21 days to end before the closure, on Thu 24 Dec; failure is complete at the end of 24 Dec, so a winding-up application in the Supreme Court waits for 4 Jan. |
| Tue 15 Dec 2026 | First day to request default judgment on a claim served 16 Nov, with eight registry days left before the closure. |
| Thu 24 Dec 2026 | Last ordinary registry day. Supreme Court eLodgments after 4:30pm are dated 4 Jan. |
| Fri 25 Dec 2026 to Fri 1 Jan 2027 | Court holidays. Nothing is filed, issued or listed in the ordinary course; in previous years a duty judge has sat for urgent matters only. |
| Mon 4 Jan 2027 | Registries reopen and, on the Supreme Court's calendar as last checked, the applications list resumes. |
How do the 21 days on a statutory demand run over Christmas?
A statutory demand under s 459E of the Corporations Act 2001 (Cth) (Corporations Act) requires a company, within 21 days after service, to pay a debt of at least $4,000 that is due and payable or to secure or compound for it to the creditor's reasonable satisfaction. Failure at the end of that period (s 459F) means the court must presume the company insolvent on a winding-up application made within the following three months (s 459C(2)(a)). The days are calendar days counted from the day after service under s 105 of the Corporations Act and s 36(1) of the Acts Interpretation Act 1901 (Cth) (Commonwealth Interpretation Act) and the court cannot extend the 21 days the company has under s 459G to apply to set the demand aside: David Grant & Co Pty Ltd v Westpac Banking Corporation (1995) 184 CLR 265. If the company does apply in time, s 459F extends the period for compliance.
Posting the demand to the registered office is service under s 109X, but the date of service then rests on a presumption about delivery that the company can try to rebut. A demand served after 3 December can still found a winding-up application in 2027, though the debtor's last day to apply under s 459G may then fall in or just after the closure; our setting aside guide and statutory demand page cover that side.
Weekends and holidays inside the 21 days count, the court's Christmas break included: in J & K Homes Pty Ltd v Evans Lawyers [2017] QSC 24 a company that left the break out of its count applied to set a demand aside 23 days after service and the Supreme Court of Queensland held the application out of time. Where day 21 itself falls on a weekend or a public holiday, s 36(2) of the Commonwealth Interpretation Act, in the form that s 5C of the Corporations Act applies, may carry the last day forward; whether it does for either 21-day period is not settled. For a demand whose day 21 falls on one of those days over the break, the answer fixes the day of failure and with it both the first day a winding-up application can rely on that failure and the last day of the three months under s 459C(2)(a).
When can a creditor request default judgment before the closure?
A defendant served with a claim has 28 days after the day of service to file a notice of intention to defend, under r 137 of the UCPR read with s 38 of the Acts Interpretation Act 1954 (Qld) (Queensland Interpretation Act). If none is filed, the plaintiff can request judgment for a debt or liquidated demand under r 283, on proof of service that meets r 282. A time to file that ends on a day the registry is closed runs to the next day it is open (s 38 of the Queensland Interpretation Act with r 976).
A notice of intention to defend filed late but before judgment defeats the request. A judgment entered without proof of service that complies with r 282 is irregular and an irregular default judgment is ordinarily set aside under r 290 without the defendant having to show a defence.
The registrar adds interest at the contract rate if the claim pleads one, otherwise at the rate set for each half-year for s 58 of the Civil Proceedings Act 2011 (Qld) by Supreme Court Practice Direction 7 of 2013 and its District and Magistrates Courts counterparts: 4% above the Reserve Bank cash rate (Queensland Courts interest rates). Costs under r 283(2)(b) are the fixed scale amounts plus court fees and service costs paid, with nothing for the letter of demand. Enforcement under chapter 19 of the UCPR is a further step and the registry issues nothing for it during the closure.
Why do subcontractors and suppliers on retention of title terms run to a different timetable?
A progress claim given in the week before Christmas
A Brisbane electrical subcontractor chasing a progress payment has a statutory route of its own under the Building Industry Fairness (Security of Payment) Act 2017 (Qld) (BIF Act). The BIF Act's definition of a business day leaves out every day from 22 December to 10 January (Queensland Building and Construction Commission guidance), so its count on a claim given from Monday 21 to Thursday 24 December does not start until Monday 11 January 2027, a week after the registries reopen. The head contractor must answer with a payment schedule within the subcontract's period or 15 business days, whichever ends first (s 76). A subcontract that counts calendar days runs straight through the break: 21 days from a claim given on Thursday 24 December run out on Thursday 14 January 2027, well before the BIF Act's own period ends. Whether a particular subcontract sets such a period and how it counts it, can only be read off the subcontract.
A wholesaler stocking a retailer for Christmas
A wholesaler stocks a regional retail chain for Christmas on terms that keep title until payment and has never registered on the Personal Property Securities Register (PPSR), which the Australian Financial Security Authority keeps. The Personal Property Securities Act 2009 (Cth) (PPSA) looks at what that clause does, which is secure the price, rather than at who holds title, so it is a security interest under s 12. If the retailer's directors appoint administrators in January while the wholesaler is still unregistered, s 267 vests the wholesaler's interest in the stock in the retailer and the wholesaler ranks with the unsecured creditors. Registering in December, once the account has gone bad, may come too late: under s 588FL of the Corporations Act a registration made more than 20 business days after the terms of trade took effect can vest the same way if administrators are appointed within six months of it.
A supplier that did register
A competitor that registered in time is better placed but cannot simply collect its stock: while administrators are in control, an owner or secured party generally needs the administrators' written consent or the court's leave under s 440B of the Corporations Act to take back goods the company holds. The competitor's priority over a bank secured across the retailer's assets also rests on the date it registered its purchase money security interest (s 62 of the PPSA). A statutory demand served in December could help a supplier like this or could bring on the appointment that fixes its position and the register and its terms of trade point one way or the other.
Matching the document to the debtor
While the registries are closed, letters of demand can still go out, a process server can be briefed for 4 January and interest keeps running. The dates say nothing about which document a particular debtor calls for. A part payment, a genuine dispute raised before any demand, an offsetting claim, a debtor that is not a company, a debt small enough for the Queensland Civil and Administrative Tribunal or a debtor with nothing to enforce against each changes the route and some of them can turn a December demand into a costs order against the creditor.
Part of a subcontractor's count is written into its own subcontract and a supplier's standing shows up in its PPSR search and terms of trade. Measuring those papers against a particular debtor is the step this timeline leaves to a lawyer. A Queensland business weighing up an overdue account before the break can call Jamie Nuich at Astris Law on (07) 3519 5616.
Frequently Asked Questions
Does a document lodged online with the Supreme Court during the court holiday count as filed that day?
It is dated Monday 4 January 2027. The Supreme Court's online portal treats a compliant document received after 4:30pm or on a day the registry is closed, as filed on the next day the registry is open.
Does the 21-day period under a statutory demand stop over the court holiday?
No. The days keep running and the court cannot extend the company's time to apply to set the demand aside. The Supreme Court of Queensland has refused to leave the Christmas break out of that count.
Sources and References
- Court rulesSupreme Court of Queensland, Practice Direction 2 of 2026, Designation of Court Holidays (31 July 2026)
- Court rulesDistrict Court of Queensland, Practice Direction 2 of 2026, Designation of Court Holidays
- Court rulesMagistrates Courts of Queensland, Practice Direction 1 of 2026, Designation of Court Holidays
- OtherQueensland Courts, Supreme Court civil applications availability (judge) calendar
- OtherQueensland Courts, electronic lodgement of civil claims, Brisbane Supreme Court
- Court rulesUniform Civil Procedure Rules 1999 (Qld), ch 19 and rr 137, 282, 283, 290 and 976
- LegislationActs Interpretation Act 1954 (Qld), s 38 (reckoning of time)
- LegislationCivil Proceedings Act 2011 (Qld), s 58 (interest up to judgment)
- OtherQueensland Courts, interest rates on debts (default judgment and money order rates)
- LegislationCorporations Act 2001 (Cth), ss 5C, 105, 109X, 440B, 459C, 459E, 459F, 459G and 588FL
- LegislationActs Interpretation Act 1901 (Cth), s 36 (calculating time, current text)
- OtherQCAT, debt dispute process
- Case lawDavid Grant & Co Pty Ltd v Westpac Banking Corporation (1995) 184 CLR 265
- Case lawJ & K Homes Pty Ltd v Evans Lawyers [2017] QSC 24
- LegislationBuilding Industry Fairness (Security of Payment) Act 2017 (Qld), s 76
- OtherQueensland Building and Construction Commission, business days and the holiday period under security of payment
- LegislationPersonal Property Securities Act 2009 (Cth), ss 12, 62 and 267
This article is for general information purposes only and does not constitute legal advice and should not be relied on as such. While we take reasonable care to ensure the accuracy of the information provided, we make no representations or warranties as to its completeness, currency or reliability. We accept no liability for any loss or damage arising directly or indirectly from the use of or reliance on, this website's content. You should always seek professional advice tailored to your specific circumstances before acting on any information in this article. Liability limited by a scheme approved under Professional Standards Legislation.
Owed money and watching the December calendar?
The amount owed, who signed the contract, what the debtor has said since and, for a subcontractor or a supplier on retention of title terms, the subcontract and the register can each send a December debt down a different route. Jamie Nuich acts for Queensland businesses owed money and can talk through a particular account by phone.